Work progress of one drinking water supply network in Samangan province

content_manager
دوشنبه ۱۳۹۸/۲/۳۰ - ۷:۳۰
Samangan

At a cost of more than AFNs 7, 2 million the construction work of one potable water supply network has been 80 completed through the Citizen’s Charter National Priority program of the Rural Rehabilitation and Development Ministry (MRRD) in Chahar Sang, Dah Now Sarbagh and Bas Esar villages of Khram district of Samangan province.

This network is 5570 meters long and has 3 taps and four water reservoirs with a total volume of 140 cubic meters of water. During the construction of the mentioned network 2000 lobar days have been created for the technical and nontechnical workers and after accomplishment 159 families will be benefited.

تازه ترین اخبار

یکشنبه ۱۴۰۵/۷/۱۹ - ۴:۲۳
Background image

وزیر محترم احیا و انکشاف دهات با متنفذین و بزرگان قومی ولایت پکتیا دیدار کرد

محترم الحاج ملا عبداللطیف منصور، وزیر احیا و انکشاف دهات، امروز در دفتر کار اش با متنفذین و بزرگان قومی گردیز مرکز ولایت‌ پکتیا دیدار نمود.

در این دیدار، متنفذین و بزرگان قومی گردیز. . .

سه‌شنبه ۱۴۰۵/۷/۱۴ - ۵:۴۱
Background image

سرک خامه واخان ولایت بدخشان تکمیل و به بهره‌ برداری سپرده شد

کار ساخت سرک خامه به طول (۱۲۱)کیلومتر از منطقه بروغیل ولسوالی واخان تا سرحد چین، به هزینه مجموعی (۳۶۵) میلیون افغانی که در دو فاز از سوی وزارت احیاء و انکشاف دهات تکمیل گردید، امروز طی. . .

یکشنبه ۱۴۰۵/۷/۵ - ۴:۳۲
Background image

کار ساخت یک پل در ولایت زابل آغاز شد

کار ساخت یک پل به طول (۴۰) متر در قریه جعفر علی خیل ولسوالی شاجوی ولایت زابل به مصرف (۱۷٫۵) میلیون افغانی توسط محترم الحاج مولوی عبدالرحمن حلیم معین مالی و اداری وزارت احیاء و انکشاف. . .

BACK TO NEWS